PROJECT TIMELINE

Subject to North Channel Wind securing relevant consents and seabed leases, it is possible that construction could commence in 2029.



2020

2022-2024

Initial stakeholder consultation, long-lead environmental surveys, scoping of environmental impact assessment


2024-2026

Environmental impact assessment (including further public consultation)


2025

Seabed agreement for lease awarded, pending a leasing round by The Crown Estate

2027

Consents achieved


2028

Financial Investment Decision


2029

Construction commences



2031

Generation commences


2031