PROJECT TIMELINE

Subject to North Channel Wind securing relevant consents and seabed leases, it is possible that construction could commence in 2030.



2020

2022-2025

Initial stakeholder consultation, long-lead environmental surveys, scoping of environmental impact assessment


2025-2027

Environmental impact assessment (including further public consultation)


2026

Seabed agreement for lease awarded, pending a leasing round by The Crown Estate

2028

Consents achieved


2029

Financial Investment Decision


20230

Construction commences



2032

Generation commences


2031