Subject to North Channel Wind securing relevant consents and seabed leases, it is possible that construction could commence in 2030.
2022-2025
Initial stakeholder consultation, long-lead environmental surveys, scoping of environmental impact assessment
2025-2027
Environmental impact assessment (including further public consultation)
2026
Seabed agreement for lease awarded, pending a leasing round by The Crown Estate
2028
Consents achieved
2029
Financial Investment Decision
20230
Construction commences
2032
Generation commences